  1. Where to go: The SECC (Scottish Exhibition & Conference Centre). You will need a set-up badge to get access to the exhibit halls.


  2. Where to pick up a set-up badge: Either at the MiMo (Move-in, Move-out) Volunteers Desk, outside of Hall 1 in the SECC. (Everybody, including the chairmen, signs in here.)

  3. Who is needed: Well, everybody who can help. We'll be doing work requiring both physical and mental exertion, as well as tasks requiring neither. There will be some interesting conversations (and no, not consisting just of, "toss me that spanner, please!"), there will probably be some giddy laughter, and there will inevitably be bad puns. This is fandom, after all. (We'll also make sure you get something to eat and something to drink and that sort of thing -- we don't want you to hurt yourself before Worldcon!)


  4. When: Our biggest needs for a large crew are on Wednesday, 3 August and Thursday, 4 August. But if you're available before that (especially if you can help set up the Art Show!), we'll be glad of your help. The schedule below gives you an idea of what we're doing, when, and where.

 

Monday, 1 August

Time People Task Location Contacts
10 a.m. 8-12 Furniture delivery arrives and is unloaded SECC Hall 1 Sparks Rennie
11 a.m. 6-10 Pre-con registration sets up SECC Hall 1 Larry van der Putte
Noon 8-12 Storage delivery from York and unpacking SECC Hall 1 Sparks Rennie
  2 Foam core delivery; redistributed to print room SECC Hall 1 Ewan Chrystal
  4-8 Art Show metal delivered; preliminary metal work done SECC Hall 1 Dave Tompkins

 

Tuesday, 2 August

Time People Task Location Contacts
9 a.m. 8-12 Delivery and unloading of construction equipment SECC Hall 3 Dave Tompkins
10 a.m. 4-6 Delivery of Souvenir Books, Con Guides, CDs SECC Hall 1 Steve Cooper, Sparks Rennie
  20-30 Construction of Art Show hangings SECC Hall 3 Dave Tompkins
10:30 a.m. 8-12 Delivery and unloading of furniture SECC Hall 3 Sparks Rennie, Glenn Glazer, Ewan Chrystal, Eamonn Patton
After Noon 4-6 Delivery and unloading/distribution of pallets from US SECC Hall 3 Sparks Rennie, Deb Geisler, Ewan Chrystal
Late afternoon 4-6 Setup of display materials for exhibits; store exhibits materials in Hall 2 (last access at 22:00) SECC Hall 3 Mark Olson

 

Wednesday, 3 August

Time People Task Location Contacts
9 a.m. 6-12 Deliveries of copyprinters, artwork & dealers shipments Halls 2 and 3 Steve Cooper, Sparks Rennie, Tim Illingworth
  10-12 Continuing set-up for Art Show, Dealers Hall 3 Julie Faith Rigby, Marcia Illingworth, Dave Tompkins
10 a.m. Log. team YAFA Delivery, setup begins Hall 3 Eamonn Patton, James Bacon, Glenn Glazer
  Log. team/hired Furniture Delivery Hall 2, Remainder Hall 1, Moat House Ewan Chrystal
10:30 a.m. 12-30 Construction of ConCourse Hall 2 Ewan Chrystal, Sparks Rennie
11 a.m. Log. team Deliver Offworld Merchandise to Sales to Members and Dealers Halls 2 and 3 Eamonn Patton
  Log. team Deliver foam boards to fan room Moat House Eamonn Patton
All day Many ConCourse Set-up Hall 2 Ewan Chrystal
All day YAFA team YAFA Set-up Hall 3 James Bacon
All day Many; art show team Art Show Set-up Hall 3 Tim Illingworth, Julie Faith Rigby
All day 4-6; set tables, cloths Dealers Set-up continues; dealers have access late p.m. Hall 3 Tim Illingworth, Marcia Illingworth

 

Thursday, 4 August

Time People Task Location Contacts
9 a.m. 30-40 or more Continue ConCourse set-up; bid/fan tables move in; all exhibitors in Hall 2 Ewan Chrystal
  PLOKTA team Set-up of Fan Room Moat House PLOKTA Cabal
  6-8 Build storage area and transfer storage Hall 5 Sparks Rennie, Glenn Glazer
  Log. team Deliveries, transfers continue SECC/Moat House Eamonn Patton
10 a.m. Art show team Artist Check-in Hall 3 Tim Illingworth, Julie Faith Rigby
  3-4 Dealer Move-in continues Hall 3 Tim Illingworth, Marcia Illingworth
Noon   Open Hall 2 to Public Hall 2  
2 p.m.   Open Dealers to Public Hall 3  
    Open Art Show to Public Hall 3  